Queensway Gateway road: ‘negative reputation will continue longer term and be hard to recover from’.

The Queensway Gateway road (QGR) is now categorised as high risk in three different categories: delivery, financial and reputational.

This was revealed in a paper presented to the South East Local Enterprise Partnership (SELEP) Strategic Board meeting on 16 March 2018. The ‘Deliverability and Risk Assessment’ document [p63] lists all the projects in the SELEP area (East Sussex, Essex, Kent, Medway, Southend and Thurrock) paid for with Local Growth Fund money.

Each project is given a rating, from one to five, in each of the three risk areas – the QGR scores 5 in each area. There is an explanation [p72] of what each number means in the RAG (‘red, amber, green’) system used by SELEP. This is the explanation for a five in each area:

SELEP RAG rating chart

Let’s look at each of those areas in turn:

1. Delivery

‘Major issues have caused significant delays (more than 3 months); processes have been interrupted or not carried out correctly (e.g. planning permission has not been secured); or significant changes have had to be made to the aims and scope of the project. Project likely to under deliver forecast project outputs.’

‘Significant delay’

According to the QGR consultation report in 2014, the QGR was due to open around a year after the Bexhill Hastings Link Road. In fact, the BHLR opened in December 2015, well over two years ago, and the QGR is very far from finished:

Queensway Gateway, Nov 2017

A recent document from ‘Team East Sussex’ – the ‘local federated board’ for SELEP – puts the blame for delays on ‘judicial reviews’ and ‘poor winter conditions’. The first judicial review (based on air pollution), it should be remembered, was successful and the second failed when SeaChange altered the figures on air pollution, citing ‘methodological errors’ in the original planning application. SeaChange also blames higher than expected tenders for the final phase of work.  The Team East Sussex report puts the finish date for the road at December 2018.

 ‘Project likely to under deliver forecast project outputs’

At the consultation stage, SeaChange forecast that the QGR would support [p10] 1,370 jobs. It’s not clear how they managed to reach this figure. What is clear, is that other local SeaChange projects are simply not creating the jobs claimed for them. Enviro 21 (built by SeaChange’s predecessor, SeaSpace) promised 500 jobs but only created 24. North Queensway Innovation Park promised 865 jobs but is currently set to create none at all. Havelock Place, SeaChange’s office project in Hastings town centre, was supposed to create 440 jobs but has created 12. In the light of those projects, the prediction of 1,370 jobs for the QGR starts to look not just optimistic but utterly deluded.

2. Finances

‘A variance of over 10% against profiled financial forecast (total expenditure) or significant changes to project finances required (increases or decreases) due to poor or delayed delivery. ‘

Given that the QGR was forecast to cost £6m and is now predicted to come in at £12m, it’s fair to say that the variance against the profiled financial forecast is rather higher than 10%.

Hastings Observer 16 February 2018

3. Reputation

‘Challenges with project are undermining LEP credibility with public or key stakeholder. This negative reputation will continue longer term and be hard to recover from.’

In order to meet the 100% increase in cost of the QGR, £2m has been raided from the budget for walking and cycling in Hastings and Bexhill. This is certainly a serious reputational issue, although no councillor from Hastings Borough Council appears to have a word to say on the issue. In addition, as SeaChange’s projects continue to fail to deliver – either in terms of timing, cost, or promised benefits – so scepticism is growing locally about whether the company should be entrusted with huge amounts of public money to build endless white elephant projects.

£2m funding cut for walking and cycling to fund Queensway Gateway Road 100% cost increase

East Sussex County Council were probably hoping that nobody would read the document enticingly named ‘Local Growth Fund – Amendments to spend profiles 2017/18‘. But we did, and what we found out was pretty worrying.

What the document shows is that the budget for two local roads being built by ‘regeneration’ company SeaChange Sussex have risen massively. Continue reading

Queensway Gateway road: ‘Project overspend is likely’

In July 2016, local group Combe Haven Defenders (CHD) sent out a press release demanding to know why SeaChange Sussex were forecasting that the cost of the Queensway Gateway road (QGR) would be only £6m, a £9m reduction on the original £15m predicted cost. Continue reading

East Sussex Strategic Growth Project: too good to be true?

The South East Local Enterprise Partnership (SELEP) agreed in January 2017 to allocate £8.2m of Local Growth Fund money to the East Sussex Strategic Growth Project (ESSGP). This is SeaChange’s next big project, and worth taking a look at in a bit of detail.
Continue reading

North Queensway Innovation Park: a second occupier but still no new jobs

SeaChange has found another occupier for its North Queensway ‘Innovation’ Park. They’ve submitted a planning application for a ‘car showroom and workshop’. One might wonder why SeaChange did not announce this with its usual chutzpah in the local press, or indeed why there is not a word about it on their website. Surely they want to announce the news of more jobs for Hastings? Continue reading

The North Bexhill Access Road: the mystery of the money

Here’s a question.  How much will SeaChange’s North Bexhill Access Road (NBAR) cost – if it’s built – and where would the money come from?

It would undoubtedly be public money – it always is – but how much of it is a bit of a mystery. Continue reading

North Bexhill Access Road: planning permission without a business case?

OLYMPUS DIGITAL CAMERA

On the route of the North Bexhill Access Road: road would run right to left through picture

On 11 September 2015,  SeaChange submitted a planning application  for the North Bexhill Access Road.  There is no date yet for the application to be considered by Rother District Council’s planning committee, but according to government guidance, major planning applications should be determined within 13 weeks, although this can be extended to 26 weeks.  Rother District Council’s planning website states that the NBAR application will be decided by 1 January 2016. Continue reading